AIS PETALAS

κατασκευαστική

Customer

PROTERGIA SA
(SPIDER ENERGY)

Role

ELECTROMEC SA as general contractor

Construction Period

2017

Project Budget

5.670.000€

Scope of Work

Electrical works
EPC of 150/20kV Substation.
Construction of underground MV cable network and f.o. cable network approx. 21.000m.
Commissioning and StartUp.

AIS MYRTIA

electormec

Customer

EREN SA

Role

ELECTROMEC SA as subcontractor for VIKO AETE

Construction Period

2017

Project Budget

2.360.000€

Scope of Work

Electrical works
Expansion of existing Substation.
Construction of underground MV cable network and f.o. cable network.
Commissioning and StartUp.

AIS MOLYKREIO

ΥΠΟΣΤΑΘΜΟΣ ΜΟΛΥΚΡΕΙΟΥ

Customer

VOLTERRA K-R SA

Role

ELECTROMEC SA as EPC contractor

Construction Period

2017

Project Budget

2.815.000€

Scope of Work

Civil and Electrical erection.

Turn key erection of 150KV Substation. Commissioning and StartUp.

AIS DESFINA

Electromechanical installations

Customer

ENERCON GmbH – AIR ENERGY SA

Role

ELECTROMEC SA as general contractor

Construction Period

2018 – 2019 (under construstion)

Project Budget

5.650.000€

Scope of Work

Civil and Electrical erection.
Turn key erection of 150KV Substation.
Overhead cable power line of approx. 13.000 m
Commissioning and StartUp.

AIS AGHIORGITIKA

Electromechanical installations

Customer

PARTHENION WIND PARK SA

Role

ELECTROMEC SA as general contractor

Construction Period

2016 – 2017

Project Budget

1.800.000€

Scope of Work
Civil and Electrical erection.

Turn key erection of 150KV Substation. Commissioning and StartUp.